Summary

Details

Page properties
Content
... ... @@ -8,8 +8,13 @@
8 8  
9 9  11 different tests will take place between the 2nd and the 6th of January 2017 in Seefeld and Innsbruck, Tyrol. Due to some software programming that might not be finished by January, tests 06, 08, 10, 12, 13 and 14 are planned for February.
10 10  
11 -The following tests have been scheduled:
11 +The test schedule is as follows:
12 12  
13 +|= |=02-Jan|=03-Jan|=04-Jan|=05-Jan|=06-Jan
14 +|Aouda.X|AM T9 Perf.Env\\PM T3-A Sensors|T5 Connectivity|T4 Radiation|AM T15, T1C Exo/Hum\\PM (none)|T1-AB, T7 Hum/Thermal
15 +|Aouda.X|T9 Perf.Env.|T3-BC, T9 Sensors/Perf.Env.|T10 Metabolic|T9 Perf.Env.|AM T2 HMI\\PM (none)
16 +|unsuited AAs|T11 Glove dex|T11 Glove dex, T16 Tesla Coil|T11 Glove dex|T11 Glove dex|T11 Glove dex
17 +
13 13  |=Test|=Description
14 14  |[[01 Humidity Test>>doc:.17A-01 Humidity Test.WebHome]]|Demonstrate that the suit performs nominal under humid or light rain conditions.
15 15  |[[02 Head-up Display / HMI>>doc:.17A-02 Head-up Display - HMI.WebHome]]|Functionalities implemented in summer 2016 should perform nominal and show up on the head-up-display and be commanded by the analog astronaut.
... ... @@ -27,3 +27,4 @@
27 27  |14 Mass budget|Mass Budget and CG
28 28  |[[15 Exoskeleton Stress Test>>doc:.17A-15 Exoskeleton stress test.WebHome]]|This test analysis the ergonomics of the exoskeleton for its next generation version.
29 29  |[[16 Tesla Coil>>doc:.17A-16 Tesla Coil.WebHome]]|A tesla coil will be deployed to test the vulnerability of the Aouda suit to lighting produced by Martian dust devils.